RAAC remediation

RAAC Roof Replacement, Phase 3

A later phase of the same RAAC programme, priced from the survey record of phase one.

Sector

Workplace

Location

South Wales

Scope

RAAC removal and reinstatement

Delivered

2026

The brief

Following the earlier phases, the remaining RAAC planks over the rear of the building were programmed for removal and replacement during the summer shutdown.

The challenge

The shutdown window was fixed and short. Materials were called off early and scaffold was struck in sections to release the areas below on time.

The result

All remaining bays were replaced inside the window, with the building fully reoccupied on the first day of term.